Infrastructure Overhaul: Why Kashmir’s Power Will Be Off This July

Infrastructure Overhaul: Why Kashmir’s Power Will Be Off This July

Infrastructure Upgrades, Utility Shifting, and the Road to Resilience

By: Javid Amin | Srinagar | 10 July 2025

Why the Lights Are Going Out

In a region where every watt counts, scheduled power shutdowns are more than just technical adjustments—they’re a reflection of Kashmir’s evolving infrastructure landscape. The Kashmir Power Distribution Corporation Limited (KPDCL) has announced a series of planned outages across Srinagar, Kupwara, and Ganderbal districts. These shutdowns are essential for utility shifting under the Comprehensive Sewerage Scheme (Zone III) and for ongoing road and infrastructure development projects.

Affected Areas and Shutdown Schedule

Srinagar District

Dates: July 12, 15, and 19 Time: 08:00 AM to 01:00 PM Reason: Utility shifting for sewerage and road works at Dr Ali Jan Road and Wanganpora link road Affected Receiving Stations:

  • Khanyar
  • Rainawari
  • Takanwari
  • SH Pora
  • Shereen Bagh
  • MR Gunj
  • Kawdara
  • Mughal Masjid

Impacted Localities: Miskeen Bagh, Rosebal, Hazaribagh, Kondebal, Hasanabad, Jogi Lankar, Palpora, Sangam, JLNM Hospital, Fatehkadal, Khayam, Khankahi Mohalla, Jamallatta, Nawabazar, Zainakadal, Firdous Colony, Zaldagar, Nowhatta, Nawa Kadal, MR Gunj, Zadibal, Kaksarai, and adjoining areas.

Kupwara District

Dates: July 10 and 14 Time: 08:00 AM to 01:00 PM Reason: Road works on Rafiabad–Kupwara–Chowkibal–Tanghdar National Highway by BEACON Affected Receiving Stations:

  • Drugmulla
  • Tikker
  • Galizoo

Impacted Localities: Drugmulla, Arampora, Kupwara Town, Baterga, Gulgam, DC Office Complex, and nearby areas.

Ganderbal & Bandipora Districts

Dates: July 13, 15, 17, 19, 21, and 22 Time: 08:00 AM to 12:00 PM Reason: Electrical utility shifting for the proposed Ring Road Affected Receiving Stations & Areas:

Line Dates Receiving Stations Impacted Areas
Badampora–Wangipora Tap July 15, 19, 22 Batwina, Wangipora, Nowgam Batwina, Nowgam, Wangipora, Zazna, Ahan, Waskura, Kharbagh, Sumbal, Nesbal
Badampora–Army Hakbara July 15, 19, 22 Hakbara, Hajin, Madwan, Army Hajin, Preng, Madwan, Banyari, Hakbara, Chandergeer
Badampora–Lar Tulmulla July 13, 17, 21 Lar, Tulmulla Lar, Tulmulla, Repora, Watlar, Waliwar, Dangerpora, Larsun

Contextual Insights: Why These Shutdowns Matter

These outages aren’t just about turning off the lights—they’re part of a broader push toward infrastructure modernization. The sewerage upgrades in Srinagar, highway expansion in Kupwara, and Ring Road development in Ganderbal and Bandipora are all critical to improving urban mobility, sanitation, and connectivity.

What’s Being Upgraded?

  • 33KV Transmission Lines: Key arteries of Kashmir’s power grid
  • Receiving Stations: Local hubs that distribute electricity to homes and businesses
  • Utility Shifting: Moving power infrastructure to accommodate new roads and sewerage systems

Navigating the Impact: What Residents Should Know

KPDCL has urged residents to cooperate during these shutdowns, emphasizing that power will be restored immediately after work completion. Here’s how to prepare:

  • Charge essential devices in advance
  • Keep backup lighting (candles, torches) ready
  • Minimize use of refrigeration during outage hours
  • Follow KPDCL updates via official channels

Final Thoughts: Powering Through Change

While temporary outages may cause inconvenience, they’re a necessary step toward a more resilient and modern Kashmir. These upgrades reflect a commitment to long-term development, improved public services, and better living standards. As Kashmir navigates its infrastructural transformation, public cooperation and awareness will be key to ensuring a smooth transition.